Time and work: add rates, not days.

Model workers, machines, filling pipes and leaks as rates; combine them correctly; and solve changing-team, efficiency and wage-sharing questions.

Illustration of Rahul Gautam guiding learners through work-rate calculations
“Time is the reciprocal of rate; the whole chapter grows from that fact.”— Rahul Gautam

Concept 1

Convert completion time into a daily rate

If A completes a job in x days, A's one-day work is 1/x. Work completed in d days is d/x. Time and rate are reciprocals when the total job is fixed.

LCM method: choose total work as the LCM of individual times. If A takes 12 days and B 18 days, take 36 units; their rates are 3 and 2 units/day.

Concept 2

Add simultaneous work rates

If A takes 12 days and B takes 18 days, together they do 1/12+1/18=5/36 per day, so time = 36/5 = 7.2 days.

For a worker who undoes work, subtract the rate. Never add or average completion times directly.

Concept 3

Efficiency and time move inversely

If efficiencies A:B=3:2, their times for equal work are 2:3. If A is 25% more efficient than B, efficiency ratio A:B=125:100=5:4, so time ratio A:B=4:5.

Workers × days × hours × efficiency is proportional to work when conditions remain comparable.

Concept 4

Split changing teams into time blocks

Calculate the work done before a worker joins or leaves, subtract it from one whole job, then use the new combined rate for the remainder.

For alternate-day work, find the work completed in one full cycle, count complete cycles, and handle the remaining day in the stated order.

Concept 5

Divide wages by actual work contribution

If workers operate for the same time, wages follow their efficiency ratio. Otherwise wages follow rate × time. A twice as efficient as B but working half as long contributes equally.

Do not divide wages merely by headcount unless every worker contributes equally.

Concept 6

Pipes use the same rate model

An inlet filling a tank in x hours has rate +1/x; an outlet emptying it in y hours has rate −1/y. Add signed rates, then invert the positive net rate to find filling time.

ActionRate signExample
FillsPositive+1/6 tank/hour
EmptiesNegative−1/9 tank/hour
NetSum1/18 tank/hour

Worked methods

Examples with reasoning

Two workers together

A takes 10 days and B 15 days. Rate=1/10+1/15=1/6, so together they take 6 days.

Find an unknown worker

A+B take 8 days; A takes 12. B's rate=1/8−1/12=1/24, so B takes 24 days.

A leaves midway

A and B rates are 3 and 2 units/day for a 30-unit job. Together for 4 days complete 20 units; B needs 5 more days for the remaining 10.

Workers and days

12 workers finish in 15 days. At equal efficiency, 20 workers need 12×15/20=9 days.

Inlet with a leak

A pipe fills in 6 hours and a leak empties in 9. Net=1/6−1/9=1/18, so the tank fills in 18 hours.

Exam traps

Errors that reverse or distort rates

Adding days

Convert times to rates before combining workers.

Efficiency in the wrong direction

Greater efficiency means less time for equal work.

Ignoring completed work

When a team changes, subtract the first block before solving the remainder.

Positive leak

Outlets and leaks have negative rates while filling.

Wrong alternate-day order

The worker who starts may also handle the final partial cycle.

Equal wages by default

Wages follow contribution, not simply the number of workers.

Original practice

Check understanding after learning

Original syllabus-aligned questions—not claimed previous-year questions.

1. A takes 10 days and B takes 15 days. How long together?
2. A and B together take 8 days; A alone takes 12. How long does B take?
3. An inlet fills in 6 hours and a leak empties in 9 hours. How long to fill the tank together?

Rapid revision

The one-minute sheet

  • Rate = 1/time for one complete job.
  • Combined rate = sum of individual signed rates.
  • Efficiency ratio is the inverse of time ratio.
  • Work ∝ workers × days × hours × efficiency.
  • Wages follow actual contribution: rate × time.
  • Inlets are positive; outlets and leaks are negative.